Pen y Cymoedd Wind Farm

The project is a 78 turbine development, Our task was installing the 132kv ducts for the grid connection cross country 3.4 k twin circuit.

Here is a timeline of what is happening when:

February 2014 – 2016: Civil and electrical works, including construction of the site welfare compound, site access tracks, turbine foundations, crane pads, underground cabling and substation
Late 2015: Turbine deliveries, civil works continue
Early 2016: Turbine installation expected to begin
Late 2016: The wind farm is commissioned
Early 2017: Project completion

Pen y Cymoedd Wind Farm

Pen y Cymoedd Wind Farm

Pen y Cymoedd Wind Farm

Pen y Cymoedd Wind Farm

Contact Contact or call (+44)7969225476

Find out how ATP's highly skilled work force successfully operate specialist equipment, leads to fast and efficient laying of cable, pipes and fibre optics with minimal ground damage.

ATP

Jason Thomas
(+44) 07969 225476
(Managing Director)

Ben James
(+44) 07557 516273
(Operations Manager)

Contact