Installation of 3x110mmduct in trefoil and 1x Ø32 duct (for fibre optics) and warning tape over 30km. Depths installed at are 1.4m. Ground conditions were particularly hard in places with fractured rock and sections of deep peat. Duct installation was completed ahead of the civil contractor completing the access roads for the windfarm construction. Reducing sub-contractor interface, pinch points and overall programme of works.

Access to and from the point of work was made challenging with ground conditions and planning restraints of alternative access possibilities. However, ATP overcome these by using a helicopter to fly the duct from the compound laydown area to the work site and laid out at one hundred meter intervals. The use of ATV Hagglunds BV206 was used for operatives to get on and off site safely and in the event of an emergency whilst providing welfare facilities during inclement weather.

Job Details

Client: Farrans
Project Name: Mynydd Y Gwair Wind Farm
Duration: Six Weeks
Location: Mynydd Y Gwair, Swansea, UK
When: March / April 2018

Mynydd Y Gwair Wind Farm

Mynydd Y Gwair Wind Farm

Mynydd Y Gwair Wind Farm

Mynydd Y Gwair Wind Farm

Mynydd Y Gwair Wind Farm

Contact Contact or call (+44)7969225476

Find out how ATP's highly skilled work force successfully operate specialist equipment, leads to fast and efficient laying of cable, pipes and fibre optics with minimal ground damage.

ATP

Jason Thomas
(+44) 07969 225476
(Managing Director)

Ben James
(+44) 07557 516273
(Operations Manager)

Contact