Installation of 11kV & 33kV (3x630mm in trefoil and 1x Ø32 duct) and warning tape over 4.5km. Depths installed at are 1.4m. Ground conditions were extremely wet due to wet weather conditions. The cable route installation was in through apple orchards with restricted access and working areas.

Hedge crossings and ditches were passed in a number of locations along the route and reinstated within twenty-four hours to minimise the environmental impact.

Job Details

Client: Kiers Services
Project Name: Sandford
Duration: Four Weeks
Location: Sandford, Winscombe, Summerset, UK
When: February / March 2018

Leimuiden 20kV

Leimuiden 20kV

Leimuiden 20kV

Leimuiden 20kV

Contact Contact or call (+44)7969225476

Find out how ATP's highly skilled work force successfully operate specialist equipment, leads to fast and efficient laying of cable, pipes and fibre optics with minimal ground damage.

ATP

Jason Thomas
(+44) 07969 225476
(Managing Director)

Ben James
(+44) 07557 516273
(Operations Manager)

Contact